When a concrete scan identifies a possible conflict at a stainless steel railing post anchor, hold the affected drilling and fabrication release until the connection designer reviews the location. Register the scan and the base plate on the same datum, identify uncertain areas, and request a written disposition. Moving a hole can affect the approved anchor group, plate and glass alignment.
Carry the same location from the scan to the plate
A report image is useful only if it can be matched to the right bay and face. Ask the scan operator to record the project location, surface, orientation, datums, covered area and uncertainty. Overlay the approved hole pattern on the same reference. A photo of paint marks with no dimension to the post or grid line is difficult to use after the marks disappear.
Classify the conflict before proposing a change
| Field record | Decision | Evidence to retain |
|---|---|---|
| Possible reinforcement conflict | Hold affected location | Overlay and written disposition |
| Uncertain scan area | Request interpretation or further survey | Scan limitations and response |
| Pattern changed by designer | Reissue affected parts and template | Approved revision and issue log |
| Matching unaffected location | Confirm existing release still applies | Location mark and approval reference |
The Hilti Steel-to-Concrete handbook describes scanning methods for locating different types of concealed items. Select the method and interpretation through qualified personnel. A reported clear area is limited to the coverage and capability of the survey. Use the project’s approval process, particularly where post-tensioning or services may be present.
Avoid solving a plate problem by changing only the field mark
A new hole can change the distance to the edge or to another anchor. A revised base can change where the post stands, where the cover seats and where the pane aligns. Give the designer the actual survey record, current plate drawing, connection details and desired post line, rather than asking the installer to shift the hole by an informal amount.
Example: mirrored plates on two balcony runs
Two balcony runs use mirror-image brackets. An overlay shows a conflict on the left run only. Isolate that plate mark and location. Keep the right run on its own approved status and record the authority for either decision. If the approved solution calls for a different plate, identify it by its own part mark so it cannot be packed or installed as the original pattern.
Release the correct information to each trade
After written approval, issue the connection and plate revisions, update the template or location schedule, and remove superseded sheets from the site issue. Where work has already started, record affected parts and holes and obtain a disposition before resuming. Include a copy of the registered scan in the record rather than relying on the revised drawing to explain why the change was made.
Can a clean scan be used as permission to drill?
No. The survey informs the connection review and site permit or clearance process. Only proceed with the released method, approved geometry and required site authorization.
See the related technical guide and the square stainless steel post product page. Use the project enquiry page to send the applicable assembly drawing and outstanding decisions.